1. Which of the following is not a requirement for procuring a contractor to complete your project?

A - Written bid documents that include all required terms and conditions, technical specifications and drawingsIncorrect.B - Communicating the basis for awarding the contractIncorrect.C - Ensuring that the contractor is a local firmCorrect.Hiring a local firm is not an essential requirement for bidding, though it may be a goal of the procurement.D - Maximizing full and open competitionIncorrect.