A CoC recipient received new construction funding 7 years ago to build a permanent supportive housing (PSH) facility. Four years later the construction was completed. What CoC responsibilities must the recipient continue to meet?
A. Submit an Annual Progress Report (APR).
B. Submit data into the CoC’s Homeless Management Information System (HMIS).
C. Continue to serve homeless participants who meet the definition of homelessness that was in place at the time of their original application.
D. All of the above.
“D” is correct. All of the options provided are correct. In general, all recipients/subrecipients receiving CoC Program funds for acquisition, rehabilitation or new construction must operate the housing or provide supportive services in compliance with the McKinney-Vento Act and the CoC Program Interim Rule for at least 15 years from the date of initial occupancy by a program participant or the date of initial service provision by the recipient and subrecipient.