Length to Complete Project

How long does a recipient/subrecipient have to complete a project? (§ 578.85)

Once a grant agreement is signed, recipients of funds for rehabilitation or new construction have certain timeframes in which they must conduct their construction activities and begin providing services.

  • Construction must begin within 9 months of signing the grant agreement (or an addendum to the agreement authorizing use of the grant funds)
  • Construction must be completed within 24 months of signing the grant agreement
  • Activities that cannot begin until after construction is completed must begin within 3 months of construction completion