Q

If a grantee or subrecipient terminates a contractor, can the grantee or subrecipient use the next lowest, responsive and responsible bidder from the original solicitation, or does the project need to be rebid?

Date Published: October 2012

Print ShareThis

A

The grantee or subrecipient may be able to award the contract to the next qualified bidder. The project does not need to be rebid, however depending on the length of time and the level of work completed on the project, the next responsible bidder should be asked to submit updated pricing information and a revised scope of services.


Tags: NSP Financial and Grants Management - Procurement