What is timeliness in the CDBG Program?

Date Published: March 2019

Print ShareThis

A

"Timely performance" means compliance with the requirement that a CDBG Entitlement grantee, or Hawaii nonentitlement county grantee, must carry out its program in a timely manner, as measured by the rate of expenditure of funds from the grantee's Line of Credit (LOC). A CDBG Entitlement grantee, in accordance with the CDBG regulations at 24 CFR 570.902, must have a balance no greater than one and one-half (1.5) times its annual grant remaining in the Line of Credit, 60 days prior to the end of the program year. HUD has a longstanding policy of reducing the next year's grant allocation of a grantee that continues to be untimely.