e-snaps FAQ
Q

May project applicants make changes to the project details (e.g., change the number of beds or the budget line items) through this consolidation process for the FY 2018 CoC Program Competition?

Date Published: June 2018

Print ShareThis

A

No. Consolidated projects must include the total number of beds, units, persons served, etc., taking information from the individual renewal project applications and adding the information together for the total amounts. Project applicants cannot use the renewal consolidation process to make changes to project applications, such as changing or reducing the number of persons served, changing or reducing the number of beds or units, etc.


Tags: e-snaps NOFAs/Notices - FY 2018 NOFA Project Application - Renewal Projects Project Application - Consolidation