The maximum amount for CoC planning costs that a Collaborative Applicant may apply for in the FY 2017 CoC Program Competition is 3 percent of the CoC’s FY 2017 Final Pro Rata Need (FPRN) or $1,250,000, whichever is less. CoCs may only submit one CoC planning project application, which must be submitted by the CoC’s designated Collaborative Applicant. Because CoC planning costs are based on 3 percent of FPRN, which is the higher of the CoC’s Annual Renewal Demand (ARD) or Preliminary Pro-Rata Need (PPRN), or $1,250,000; whichever is less, the amount a Collaborative Applicant may request can fluctuate from year to year depending on the CoC's FPRN.